Turn your production plan into workload.
Spot overloads and simulate your capacity.
3 of 6 work centers overloaded
Bottleneck: SOU · Welding · peak 156% · Week 20 · May 17 – May 23, 2027
Load and capacity
- Load
- 77.8 h
- Capacity
- 50 h
- Overload
- 27.8 h
- Overtime needed
- 16 h
Orders loading the period 3
- OF-270133CHS-200 · 210 · op 3032.5 h
- OF-270137BRK-110 · 380 · op 3025.8 h
- OF-270134CAD-750 · 60 · op 1019.5 h
Load heatmap
Click a cell to see the orders loading it.
| Work center | W14 | W15 | W16 | W17 | W18 | W19 | W20 | W21 |
|---|---|---|---|---|---|---|---|---|
| Work center | Peak | Overload | Uncovered overload |
|---|---|---|---|
| 156% W20 | 74.2 h | 26.8 h | |
| 161% W16 | 37.3 h | 25.3 h | |
| 131% W18 | 17.5 h | 9.5 h | |
| 82% W18 | 0 h | 0 h | |
| 81% W20 | 0 h | 0 h | |
| 75% W20 | 0 h | 0 h |
Production capacity planning: from routing to utilization
- 1. Import
Production plan, routings and capacity from Excel or CSV. One workbook with three sheets is enough; the example shows the expected format.
- 2. Read the heatmap
Each cell crosses a work center and a period. Green: headroom. Amber: tight. Orange: overtime needed. Red: uncovered overload.
- 3. Simulate
Move a work order, change a quantity, add overtime or capacity. The effect on overloads shows up immediately.
- 4. Export
Excel workbook with load, capacity, gaps, contributing orders, baseline and modified scenarios, assumptions and issues.
Load (h) = Σ orders × operations [ setup per lot + quantity × cycle time ] · Utilization = load ÷ available capacity
Frequently asked questions
How do I calculate workshop load from a production plan?
For each work order, multiply the quantity by the cycle time of every routing operation, then add the setup time once. Sum these hours by work center and period: that is the load. CapacityLab does this from your Excel or CSV files, with no formulas to write.
How do I compute utilization and find a bottleneck?
Utilization = loaded hours ÷ available hours. Above 100%, the work center is overloaded for that period. The bottleneck is the work center with the most overload hours. The heatmap shows them in red and the bottleneck table ranks them.
Which files do I need?
Three tables, as sheets of one workbook or separate files: the production plan (order, product, quantity, date or week), routings (product, operation, work center, setup time per lot, cycle time per unit) and capacity (work center, period, available hours or shifts, overtime possible). Columns are detected automatically; download the Excel template to start from an example.
How do I simulate overtime or move an order?
Click Simulate, or Move next to a contributing order. You can move a work order, change a quantity, add overtime or change capacity. Results update instantly and compare overload before and after. Undo and Reset take you back.
Is this a scheduling tool?
No. CapacityLab is an infinite-capacity load calculation: it shows where and when load exceeds capacity, without sequencing operations. It is the capacity check (rough-cut or CRP style) that comes before scheduling.
Is my data sent to a server?
No. Files are read, calculated and exported in your browser. Nothing is uploaded and no account is needed. Closing the tab clears the session, so export your scenario first.
Calculation assumptions
- Load
- For each order and each operation of its routing: load = setup time (once per order, one order being one lot) + quantity × cycle time. A rate in units/hour becomes 1 / rate. Seconds and minutes are converted to hours. A duplicate operation counts once; two distinct operations on the same work center are added.
- Dates and calendar
- An order dated on a day is loaded on that day; dated on a week (2027-W15) or month (2027-04), its load is spread over the working days of the period. An order dated on a closed day is loaded on the previous working day. ISO weeks run Monday to Sunday.
- Capacity
- A dated row gives the hours of that period, spread over its working days. An undated row repeats every day, week or month; a closed day removes its share. Without hours, capacity is shifts × shift length × working days. Efficiency applies to available hours.
- Overload and overtime
- Overload = max(0, load − capacity) per work center and period. Overtime needed = min(overload, overtime possible). The rest is uncovered overload. Spare capacity in one work center or period never offsets another one’s overload.
- Bottleneck
- The bottleneck is the work center with the most overload hours; on a tie, the one with the highest peak utilization. Overload depends on the period size: a month sums the load and capacity of its weeks and can smooth a weekly peak.
- Limits
- Infinite-capacity load simulation: no scheduling, sequencing or precedence between operations. All operations of an order are loaded on its date. A work center without declared capacity is flagged instead of assumed.